Summary
The Limonite trail was approved as concrete but built as asphalt because city staff signed off years ago. Fixing it now could cost over $1 million and lacks a legal 'nexus' to charge this project, so the council tabled the fight for future negotiations.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 15, 2026.
Impact analysis
Tearing out and replacing the asphalt was estimated at over $700,000 four years ago — likely more now.
Residents along Limonite would benefit from a concrete sidewalk upgrade.
If negotiated later, the cost could be passed to homeowners in the new phase through Mello-Roos and housing prices.
Mentions & discussions (1)
Related development
Paradise Knolls Planning Area 5 — TTM 39007
Brings the city 221 homes, seven acres of public parks, and trail connections, but adds traffic to Limonite Avenue.
Tentative Tract Map No. 39007 (Master Application No. 24067)
The project would add 221 homes to the area, bringing new residents, traffic, and demand for services; the appeal hearing gave objectors a chance to challenge the approval.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Jurupa Valley
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.